A bill of materials (BoM) is the recipe for a product: which components go in, how many, and how much one run makes. Manufacturing orders follow it to take the components out of stock and put the finished product in.

Steps

  1. Open Manufacturing and click New BoM. Bills of materials lists the ones you have.

    Open Manufacturing
  2. Choose the product you make and how many one run makes. For example, one 25 kg bag fills 5 packs, so one run makes 5.

    Product and quantity made
  3. Add the components. Pick each component and the quantity one run uses. Click + Add component for the next one.

    Add the components
  4. Add the labour and overhead per unit (optional) and a name such as Machine packing. The estimated cost per unit at today's costs is shown below.

    Labour, overhead and name
  5. Click Save. The BoM shows what it makes, each component with its cost now, and the cost of one run.

    Save it

Tip A product can have several BoMs, for example Hand packing and Machine packing. Tick Default BoM for this product on the one new orders should use.

Good to know

  • Components and finished products are ordinary stock items in Inventory.
  • Changing a BoM doesn't change orders already produced. Archive a BoM you no longer use; its history stays.